3CE REQUEST FOR PROPOSAL
Front of the Meter Battery Energy Storage System Capacity and Energy Delivery
Monterey Bay Community Power (MBCP) is seeking to acquire up to 100 MWs of Capacity, Energy, and any associated Ancillary Products from battery storage projects in the state of California, or at the first point of interconnection, with deliveries beginning as early as January 1st, 2021, but no later than December 31st, 2022.
Supporting Documents:
Content:
Monterey Bay Community Power (MBCP) hereby issues this Request for Offers for the sale and purchase of Front of the Meter (FTM) Battery Energy Storage System (BESS) capacity and energy delivery consistent with the terms and provisions in this Request for Offers (RFO). MBCP is seeking to acquire up to 100 MWs of Capacity, Energy, and any associated Ancillary Products from battery storage projects in the state of California, or at the first point of interconnection, with deliveries beginning as early as January 1st, 2021, but no later than December 31st, 2022, on the terms set forth herein, to help MBCP meet its long-term portfolio objectives.
Activity | Scheduled Date |
Issuance of RFO | September 13, 2019 |
Seller Webinar Seller Webinar Presentation |
September 27, 2019 at 1:00 PM PPT |
Deadline to submit questions | October 2, 2019 at 5:00 PM PPT |
Responses to questions provided | October 8, 2019 |
Responses due to MBCP | October 11, 2019 at 5:00PM PPT |
Notification of final shortlisted Offers (Tentative) | October 2019 |
PPA negotiations | October 2019 – February 2020 |
Execution of PPA | February 2020 |